What Is Construction Administration? The Architect's Guide
What construction administration (CA) is, when the phase starts and ends, the architect's duties during construction, and a CA checklist from kickoff to closeout.
Construction administration (CA) is the architect's work during construction: answering the contractor's questions, reviewing submittals, visiting the site, handling changes, certifying payments and closing the project out. It is the last phase of basic services, and the one where the drawings meet the building.
On AIA contracts, the architect's construction phase services are described in Section 3.6 of the owner-architect agreement (B101-2017), and the architect's role in administering the construction contract is set out in Section 4.2 of the General Conditions (A201-2017). This guide covers what the phase includes, what it doesn't, and a checklist you can run on every project.
When construction administration starts and ends
Under B101-2017, construction phase services begin with the award of the construction contract and end when the architect issues the final Certificate for Payment. Your agreement may define it differently, so check the dates before you plan staffing and fee.
In practice, CA work starts a little earlier than that, with the pre-construction meeting, and the record keeping continues until the last warranty and closeout document is filed.
What the architect does during construction
Answering questions: RFIs
The contractor sends a request for information (RFI) when the documents are unclear, incomplete or in conflict. The architect answers in writing, within the time the contract or the schedule allows. Every RFI and response belongs in an RFI log. See what an RFI is and how architects answer them.
Reviewing submittals
Shop drawings, product data and samples come to the architect for review against the design intent. The architect returns each one with a review action such as "no exception taken", "approved as noted" or "revise and resubmit". See the submittal process and what the review stamps mean.
Visiting the site and reporting
The architect visits the site at intervals appropriate to the stage of construction, to become familiar with the progress and quality of the work and to check that it generally follows the contract documents. Each visit ends in a written field report with observations, photos and open issues. The free architect field report template has a standard layout.
Running or attending OAC meetings
The regular owner-architect-contractor meeting is where schedule, RFIs, submittals and changes are reviewed and action items are assigned. See OAC meeting agenda and minutes.
Handling changes
Changes move through a chain of documents: the architect's supplemental instruction for minor changes with no cost, the proposal request to price a change, the construction change directive when work must proceed before the price is agreed, and the change order that records the agreed change to the contract sum and time. See ASI vs. proposal request vs. CCD vs. change order, what an ASI is and construction change directives.
Certifying payments
Each month the contractor submits an application for payment. The architect reviews it against the work observed on site and certifies the amount due, or explains why part of it is withheld.
Closing out the project
At substantial completion the architect inspects the work, the punch list of items to finish or correct is agreed, and the certificate of substantial completion is issued. At final completion the architect confirms the punch list is done, collects the closeout documents the contract requires (warranties, operation and maintenance manuals, record documents) and issues the final Certificate for Payment. The free punch list template keeps items, responsibility and status in one place.
What construction administration is not
The architect administers the contract, but doesn't run the construction. Under A201-2017, the architect is not responsible for the contractor's construction means, methods, techniques, sequences or procedures, or for safety on the site. Those belong to the contractor.
Site visits are also not continuous inspection. Unless the agreement adds it, the architect observes the work at intervals and reports what it sees. It doesn't supervise each trade.
Keeping that line clear in field reports, RFI answers and meeting minutes protects the firm. Write what you observed and what the documents require, not instructions on how to build it.
Why CA is hard to keep profitable
CA is usually paid as a fixed share of the fee, while the amount of work depends on things the architect doesn't control: the quality of the contractor's submittals, the number of RFIs, owner changes and schedule slips. A project that runs long or changes often can use up the CA fee well before closeout.
The firms that keep CA under control tend to do three things:
- Track everything in one record. RFIs, submittals, changes and field issues in logs that agree with each other, not in separate spreadsheets and email threads.
- Watch the open items. Overdue RFIs, submittals waiting on a consultant, CCDs without a change order. These are where time and disputes come from.
- Report the contract sum clearly. Agreed change orders and pending changes shown separately, so the owner always knows the real number.
Construction administration checklist
Before construction starts
- Confirm the CA scope, site visit frequency and fee in the owner-architect agreement
- Read the general and supplementary conditions for RFI, submittal and change procedures
- Set up the project directory: owner, contractor, consultants, contacts
- Set up the RFI, submittal, ASI, change and punch list logs
- Agree the submittal schedule with the contractor
- Hold the pre-construction meeting. Use the pre-construction meeting agenda
During construction
- Answer RFIs within the agreed time and log each response
- Review submittals and log the action taken and the dates
- Visit the site at the agreed intervals and issue a field report after each visit
- Run or attend OAC meetings and issue minutes with action items
- Issue ASIs, proposal requests, CCDs and change orders, and keep the change chain linked
- Review and certify each application for payment
- Track open items: overdue RFIs, outstanding submittals, unsettled CCDs
At substantial completion
- Receive the contractor's notice and list of incomplete work
- Inspect the work and agree the punch list
- Issue the certificate of substantial completion
At final completion
- Confirm every punch list item is complete
- Collect warranties, operation and maintenance manuals and record documents
- Confirm every CCD is settled by a change order
- Issue the final Certificate for Payment
- Archive the project record: logs, field reports, minutes and issued documents
The free construction administration log workbook has a tab for each log in this checklist, with summaries of what is open.
Frequently asked questions
Is construction administration the same as contract administration?
They are often used interchangeably. "Contract administration" is the more common term in Canada and in some contracts, because the architect administers the construction contract between the owner and contractor. "Construction administration" is more common in the US.
Who does construction administration in an architecture firm?
Usually the project architect, a dedicated CA manager, or the principal on smaller projects. Larger firms often have a CA team that takes over from the design team when construction starts.
Does the architect have to do construction administration?
Not always. Owners sometimes leave CA out of the architect's scope or hand it to a construction manager. That carries risk: nobody who knows the design intent reviews the submittals or the changes. Many firms prefer to keep CA in their scope for that reason.
What's the difference between construction administration and construction management?
Construction management is the contractor's or construction manager's work of building the project: scheduling, buying, managing trades and safety. Construction administration is the architect's work of administering the contract and checking the work against the documents.
One record for the whole CA phase
In Agradium, RFIs, submittals, ASIs, proposal requests, CCDs, change orders, field reports, meeting notes and punch lists live in one project record, with due dates, overdue flags and a contract sum that carries forward from one change order to the next. If you would like to see it on a project, request a demo.
AIA document numbers and sections are cited to identify them. This is general information, not legal advice; your contract governs. Agradium is not affiliated with or endorsed by the American Institute of Architects.