What Is an RFI in Construction?

What an RFI (request for information) is, who sends and answers it, how fast the architect must respond, and what to do when the answer changes cost or time.

Agradium8 min read

An RFI, short for request for information, is a written question about the contract documents, sent during construction, usually by the contractor to the architect. It asks the design team to clarify something the drawings and specifications don't answer clearly: a dimension that doesn't close, a detail that conflicts with a specification, a condition in the field that the documents didn't anticipate. AIA's standard form for it is G716.

RFIs are the most frequent document on most projects, and the one that tells you the most about how a job is going. This guide covers what an RFI is for, who sends and answers it, how fast the answer is due, what goes in a good response, and what to do when the answer changes cost or time.

What RFI means in construction

In construction, RFI means request for information. The term is the same in architecture and in contracting: on a building project, it always refers to a question about the contract documents asked during construction.

It is different from the RFI used in purchasing, where a "request for information" asks vendors about their services before a bid. That one happens before a contract exists. A construction RFI happens after it.

What an RFI is for

A contractor sends an RFI when it can't build from the documents as they are:

  • Conflicts. The drawings and the specifications say different things, or two drawings disagree.
  • Missing information. A dimension, a detail or an elevation isn't shown.
  • Field conditions. Existing construction is different from what the drawings show, which is common in renovations.
  • Coordination. Two systems want the same space, such as a duct and a beam.
  • Interpretation. The intent of a detail or specification isn't clear.

What an RFI is not for:

  • Not a change. An RFI asks a question. If the answer changes the work in a way that costs money or time, the change goes into its own document.
  • Not a substitution request. A request to use a different product follows the substitution procedure in the specifications.
  • Not a submittal. Shop drawings, product data and samples go through the submittal process, not as RFIs.

Who sends an RFI and who answers it

On most projects, the contractor sends RFIs and the architect answers them. Subcontractors send their questions to the contractor, which reviews them and forwards them under its own number. That keeps one sequence of RFIs per project and keeps the contractor responsible for what it asks.

Under the 2017 edition of AIA A201, the General Conditions, the contractor has to report errors, inconsistencies and omissions it finds in the documents to the architect as a request for information (Section 3.2.2). The architect responds in writing, within any time limit the parties agreed or otherwise with reasonable promptness, and issues supplemental drawings or specifications when the answer needs them (Section 4.2.14).

When a question belongs to an engineer, such as a structural connection or a duct size, the architect sends it to that consultant, gets the answer back, and replies to the contractor. The RFI is still the architect's: the response goes out under the architect's name, and the clock keeps running while the consultant works on it.

How long the architect has to respond

As long as the contract allows. Many projects set the RFI response time in Division 01 of the specifications or in the owner-architect agreement. Seven calendar days is common, sometimes with a shorter time for urgent questions and a longer one for questions that need a consultant.

A few practical rules:

  • The clock starts when the RFI arrives, not when someone opens it. Log the received date the same day.
  • A consultant's time counts. Track when you sent the question out and when it came back, so you know where the delay was.
  • An incomplete RFI can be returned. If the question has no references or can't be understood, return it the same day with what is missing, rather than letting it sit.
  • Review overdue RFIs at every OAC meeting. An RFI that is late on the architect's side becomes the contractor's reason for a delay claim.

What goes in an RFI

A complete RFI includes:

  • The project header: project name and number, the contract, the owner, the contractor and the architect.
  • The RFI number and date.
  • The question, one per RFI, in plain words.
  • References: drawing sheets and details, specification sections, photos.
  • The contractor's suggested solution, if it has one. This often makes the answer faster.
  • Whether the contractor expects an impact on cost or schedule.
  • The date an answer is needed to avoid delaying the work.

The response adds:

  • The architect's answer, with any sketches or revised drawings.
  • Who answered and when.
  • A note that the answer does not authorize a change to the contract sum or time.

How to write a good RFI response

  • Answer the question that was asked. If the RFI raises two questions, answer both, or ask for it to be split.
  • Point to the documents. "Provide the waterproofing shown in detail 7/A-501" is better than "see drawings".
  • Keep the answer within the documents' intent. An RFI response clarifies. It shouldn't quietly redesign.
  • Say when the answer changes the work. If the answer needs a revised drawing, issue it as an ASI and reference the RFI. If it changes cost or time, start the change process.
  • Don't approve substitutions or means and methods in an RFI. Send substitutions to their procedure, and leave means and methods with the contractor.

When an RFI answer becomes a change

An RFI answer should never change the contract sum or time on its own. When it needs to, the RFI starts a chain of documents:

  • No cost, no time: the answer goes out as an ASI.
  • Cost or time, and there is time to price it: a proposal request asks the contractor for a price.
  • Cost or time, and the work can't wait: a construction change directive directs the work, and the price is settled later.

Each of these ends in a change order if the cost or time changes. The full chain is in ASI vs. proposal request vs. CCD vs. change order.

RFI vs submittal vs ASI

RFISubmittalASI
PurposeAsks a question about the documentsShows how the contractor will meet themClarifies or makes a minor change
Who starts itThe contractorThe contractorThe architect
The architect's replyAn answerA review action on the stampIt is the architect's instruction
Changes cost or time?NoNoNo
AIA formG716None; the format comes from the specificationsG710

The difference between an RFI and a submittal comes up often. An RFI asks what the documents mean. A submittal shows the contractor's plan to meet them, such as shop drawings for a stair or product data for a door, and gets a review action instead of an answer.

How to log RFIs

Number RFIs in sequence per project, in the order they arrive, and never reuse a number. A useful RFI log has these columns:

  • RFI number, subject and date received
  • How it came in: email, the contractor's project platform, or a meeting
  • Date due, calculated from the response time
  • The consultant it went to, the date sent and the date back
  • Date answered, and a short note of the answer
  • Status: open, with consultant, answered, closed or void
  • Days open, and whether it is overdue
  • The ASI, proposal request or change it led to, if any

The free RFI log template has these columns, calculates the due dates and days open, and flags overdue RFIs.

Common mistakes

  • Not logging the received date. Without it, nobody can show the answer was on time.
  • Answering by phone. A spoken answer isn't a record. Confirm it in writing on the RFI.
  • Letting RFIs carry changes. An answer that adds work, with no ASI or proposal request behind it, becomes a claim later.
  • Bundling questions. One RFI with five questions can't be closed until all five are answered.
  • Losing track of consultant time. If an RFI is late, you need to know whether it sat on your desk or an engineer's.

Frequently asked questions

What does RFI stand for in construction?

Request for information: a written question about the contract documents, usually from the contractor to the architect, asked during construction.

How long does an architect have to answer an RFI?

As long as the contract allows, often 7 calendar days, set in Division 01 or the owner-architect agreement. Without a stated time, the response is expected with reasonable promptness.

Is an RFI response part of the contract?

The response clarifies the contract documents, and the contractor builds from it, so keep it with the project record. It doesn't change the contract sum or time on its own. Those change only through a change order, or a construction change directive while the price is open.

What is the difference between an RFI and a submittal?

An RFI asks a question about the documents. A submittal, such as a shop drawing or product data, shows how the contractor plans to meet them and receives a review action from the architect.

Who pays for the work an RFI answer requires?

It depends on the answer and the contract. If the answer only clarifies the documents, there is no change. If it adds work, the contractor's remedy is a change in the contract sum or time, agreed through the change process. That is why an answer that adds work should start a proposal request or a CCD, not stay in the RFI.

Keeping RFIs in one record

In Agradium, an RFI is numbered when you log it, and its due date is set from the project's response time and kept, so a later change to the setting never moves history. You record when it went to a consultant and came back, and its status follows from those dates: open, with consultant, answered or closed. The question is stored as a PDF in your letterhead when it is logged, and again with your answer when you respond. If you would like to see it on a project, request a demo.

AIA document numbers and A201 sections are cited to identify them. This is general information, not legal advice; your contract governs. Agradium is not affiliated with or endorsed by the American Institute of Architects.

Change management

ASI vs. Proposal Request vs. CCD vs. Change Order

RFIs, ASIs, proposal requests, CORs, CCDs and change orders compared: who starts each one, whether it changes cost or time, who signs, and how they connect.

5 min read

See your next project in Agradium.

A 30-minute walkthrough, from the first RFI to a signed change order.

Request a demo