RFIs and submittals
What Is an RFI in Construction?
What an RFI (request for information) is, who sends and answers it, how fast the architect must respond, and what to do when the answer changes cost or time.
8 min read
Free template
Most RFI log templates are written for the contractor who asks the question. This one is for the architect who answers it: when the RFI arrived, when it went to a consultant and came back, what you said, and how long it took.
Free · .xlsx for Microsoft Excel · No sign-up
One log tab and a Summary tab. Each column heading in the file carries the same note as below.
| Column | What goes in it |
|---|---|
| RFI # | Number RFIs in the order you receive them, and never reuse a number. |
| Received | The date the RFI reached your office. The clock starts here. |
| Received Via | How it arrived. Dropdown: Email, Procore, Cloud, Meeting, Phone, Delivery. |
| Question | The contractor's question, in their words or a short summary. |
| Due | Calculated: the received date plus the RFI response time on the Summary tab. |
| Consultant | The consultant who answers, if it isn't your office. |
| Sent to Consultant | The date you forwarded the RFI. |
| Back From Consultant | The date the consultant's answer came back. |
| Response | The answer you sent. If it changes cost or time, say so and start the change process. |
| Answered | The date you sent the response. Leave blank while the RFI is open. |
| Sent Via | How the response went out. Dropdown: Email, Procore, Cloud, Meeting, Phone, Delivery. |
| Days Open | Calculated: days from received to answered, or to today while open. |
| Status | Calculated: Open, Overdue (past due and unanswered) or Answered. |
On the Summary tab, enter the project name and number, and the RFI response time your contract allows.
Add a row on the RFI Log tab for each RFI the day it arrives: number, received date, how it came in, and the question.
If a consultant answers it, record the dates you sent it out and got it back.
When you reply, enter the response and the date. The status changes to Answered.
Filter by Status to see what is open or overdue before each OAC meeting.
In Agradium, RFIs are numbered when you log them, due dates and response times are computed from the project's settings, and anything overdue is flagged. The log is a view of the RFIs themselves, so nobody keeps it by hand.
Questions
As long as the contract allows. Many projects set the response time in Division 01 of the specifications, and 7 calendar days is common. Enter your project's number on the Summary tab and the log calculates every due date from it.
It shouldn't on its own. An RFI response clarifies the documents. If the answer changes cost or time, say so and start the change process, usually with an ASI or a proposal request.
It is built for Microsoft Excel. You can also upload it to Google Drive and open it with Google Sheets.
RFIs and submittals
What an RFI (request for information) is, who sends and answers it, how fast the architect must respond, and what to do when the answer changes cost or time.
8 min read
Excel workbook · 11 tabs
Every log in one workbook, with a summary of what is open, what is overdue and the contract sum to date.
Free download
Excel
Logged by spec section, item and revision, with review actions and review times.
Free download
A 30-minute walkthrough, from the first RFI to a signed change order.