Most RFI log templates are written for the contractor who asks the question. This one is for the architect who answers it: when the RFI arrived, when it went to a consultant and came back, what you said, and how long it took.

Download the Excel file

Free · .xlsx for Microsoft Excel · No sign-up

What's in the file

One log tab and a Summary tab. Each column heading in the file carries the same note as below.

ColumnWhat goes in it
RFI #Number RFIs in the order you receive them, and never reuse a number.
ReceivedThe date the RFI reached your office. The clock starts here.
Received ViaHow it arrived. Dropdown: Email, Procore, Cloud, Meeting, Phone, Delivery.
QuestionThe contractor's question, in their words or a short summary.
DueCalculated: the received date plus the RFI response time on the Summary tab.
ConsultantThe consultant who answers, if it isn't your office.
Sent to ConsultantThe date you forwarded the RFI.
Back From ConsultantThe date the consultant's answer came back.
ResponseThe answer you sent. If it changes cost or time, say so and start the change process.
AnsweredThe date you sent the response. Leave blank while the RFI is open.
Sent ViaHow the response went out. Dropdown: Email, Procore, Cloud, Meeting, Phone, Delivery.
Days OpenCalculated: days from received to answered, or to today while open.
StatusCalculated: Open, Overdue (past due and unanswered) or Answered.

How to use it

  1. On the Summary tab, enter the project name and number, and the RFI response time your contract allows.

  2. Add a row on the RFI Log tab for each RFI the day it arrives: number, received date, how it came in, and the question.

  3. If a consultant answers it, record the dates you sent it out and got it back.

  4. When you reply, enter the response and the date. The status changes to Answered.

  5. Filter by Status to see what is open or overdue before each OAC meeting.

When the spreadsheet gets busy

In Agradium, RFIs are numbered when you log them, due dates and response times are computed from the project's settings, and anything overdue is flagged. The log is a view of the RFIs themselves, so nobody keeps it by hand.

Questions

Frequently asked questions

How long does an architect have to answer an RFI?

As long as the contract allows. Many projects set the response time in Division 01 of the specifications, and 7 calendar days is common. Enter your project's number on the Summary tab and the log calculates every due date from it.

Can an RFI response change the cost or time?

It shouldn't on its own. An RFI response clarifies the documents. If the answer changes cost or time, say so and start the change process, usually with an ASI or a proposal request.

Does it work in Google Sheets?

It is built for Microsoft Excel. You can also upload it to Google Drive and open it with Google Sheets.

Keep going

RFIs and submittals

What Is an RFI in Construction?

What an RFI (request for information) is, who sends and answers it, how fast the architect must respond, and what to do when the answer changes cost or time.

8 min read

Excel workbook · 11 tabs

Construction Administration Log

Every log in one workbook, with a summary of what is open, what is overdue and the contract sum to date.

Free download

Excel

Submittal Log

Logged by spec section, item and revision, with review actions and review times.

Free download

See your next project in Agradium.

A 30-minute walkthrough, from the first RFI to a signed change order.

Request a demo