ASI vs. Proposal Request vs. CCD vs. Change Order
RFIs, ASIs, proposal requests, CORs, CCDs and change orders compared: who starts each one, whether it changes cost or time, who signs, and how they connect.
5 min read
Free template
A change order request (COR) is the contractor's own request for more money or time, sent on its own form with its own number. This log keeps every COR in one place: when it arrived, what it asks for, and which change order it ended up on, so no request is left open at closeout.
Free · .xlsx for Microsoft Excel · No sign-up
One log tab and a Summary tab. Each column heading in the file carries the same note as below.
| Column | What goes in it |
|---|---|
| COR # | The contractor's change order request number. |
| Received | The date the request reached your office. |
| Description | What the contractor is asking for, and why. |
| Cost | The amount requested. Negative for a credit. |
| Time (Days) | The change in contract time requested. |
| CO # | The change order that includes it. |
| Status | Calculated: Open or the change order it is on. |
On the Summary tab, enter the project name and number.
Add a row for each COR the day it reaches your office: the contractor's number, the received date, a description, and the cost and time requested.
Enter a credit as a negative cost.
When a change order includes the request, enter its number in the CO # column. The status changes from Open to the change order it is on.
Before each OAC meeting, filter by Status to see the open requests and their total value.
In Agradium, a contractor's request is numbered when it is logged and opens its change in the change process. Approving it moves it toward a change order, and one change order can settle several requests, proposal requests and CCDs at once.
Questions
A request from the contractor for an adjustment to the contract sum or time, usually because of a condition or instruction it believes is a change. It is not a change order: it only becomes part of the contract once a change order that includes it is signed.
The architect issues a proposal request to ask the contractor to price a change. The contractor sends a COR to ask for a change on its own initiative. Both end in a change order if the owner agrees.
Yes. Enter the same CO # on each request it includes. The log shows every request on that change order, and none of them stays open.
Change management
RFIs, ASIs, proposal requests, CORs, CCDs and change orders compared: who starts each one, whether it changes cost or time, who signs, and how they connect.
5 min read
Excel workbook · 11 tabs
Every log in one workbook, with a summary of what is open, what is overdue and the contract sum to date.
Free download
Excel
Due dates, consultant hand-offs, days open and overdue flags, calculated for you.
Free download
A 30-minute walkthrough, from the first RFI to a signed change order.