Change Order Log Template for Architects (Excel)

The most common mistake in a change order log is counting a change order before everyone has signed it. This template counts a change order toward the contract sum and time only when the architect, owner and contractor have all signed, and never counts a voided one.

Download the Excel file

Free · .xlsx for Microsoft Excel · No sign-up

What's in the file

One log tab and a Summary tab. Each column heading in the file carries the same note as below.

ColumnWhat goes in it
CO #Number change orders in the order you issue them. Never delete a row: mark a cancelled change order Voided instead.
DateThe date you issued the change order.
DescriptionWhat the change order covers, including the PRs, CORs or CCDs it settles.
Change ReasonWhy the change happened. Dropdown: Owner Directed, Concealed Conditions, Error or Omission, Improvement.
CostThe change in contract sum. Negative for a credit.
Time (Days)The change in contract time. Negative to shorten it.
Architect SignedThe date the architect signed.
Owner SignedThe date the owner signed.
Contractor SignedThe date the contractor signed.
VoidedThe date the change order was voided, if it was. A voided change order never counts.
StatusCalculated: Approved only when all three parties have signed and it isn't voided.
Contract Sum AfterCalculated: the original contract sum plus every approved change order up to this row.

How to use it

  1. On the Summary tab, enter the original contract sum and substantial completion date from the owner-contractor agreement.

  2. Add a row for each change order when you issue it: number, date, description, reason, cost and time.

  3. Enter each signature date as it comes back. The status turns Approved when all three are in.

  4. If a change order is cancelled, enter the date under Voided instead of deleting the row, so the numbers stay in sequence.

  5. Read the contract sum and substantial completion date to date on the Summary tab.

When the spreadsheet gets busy

Agradium counts a change order only when the owner, architect and contractor have all signed, and voided orders never count. Each change order shows the original contract sum, the net change from earlier orders, and the new contract sum and time.

Questions

Frequently asked questions

When does a change order count toward the contract sum?

When the owner, architect and contractor have all signed it. Until then it is pending, so this log shows its value separately as awaiting signatures.

How do I record a credit?

Enter the cost as a negative number. A credit lowers the contract sum to date the same way an addition raises it.

Is this a change order form?

No. It is a log of your change orders, not the change order document itself. Issue each change order on the form your contract requires, and use the log to keep track of them.

Keep going

Change management

ASI vs. Proposal Request vs. CCD vs. Change Order

RFIs, ASIs, proposal requests, CORs, CCDs and change orders compared: who starts each one, whether it changes cost or time, who signs, and how they connect.

5 min read

Excel workbook · 11 tabs

Construction Administration Log

Every log in one workbook, with a summary of what is open, what is overdue and the contract sum to date.

Free download

Excel

RFI Log

Due dates, consultant hand-offs, days open and overdue flags, calculated for you.