ASI vs. Proposal Request vs. CCD vs. Change Order
RFIs, ASIs, proposal requests, CORs, CCDs and change orders compared: who starts each one, whether it changes cost or time, who signs, and how they connect.
5 min read
Free template
The most common mistake in a change order log is counting a change order before everyone has signed it. This template counts a change order toward the contract sum and time only when the architect, owner and contractor have all signed, and never counts a voided one.
Free · .xlsx for Microsoft Excel · No sign-up
One log tab and a Summary tab. Each column heading in the file carries the same note as below.
| Column | What goes in it |
|---|---|
| CO # | Number change orders in the order you issue them. Never delete a row: mark a cancelled change order Voided instead. |
| Date | The date you issued the change order. |
| Description | What the change order covers, including the PRs, CORs or CCDs it settles. |
| Change Reason | Why the change happened. Dropdown: Owner Directed, Concealed Conditions, Error or Omission, Improvement. |
| Cost | The change in contract sum. Negative for a credit. |
| Time (Days) | The change in contract time. Negative to shorten it. |
| Architect Signed | The date the architect signed. |
| Owner Signed | The date the owner signed. |
| Contractor Signed | The date the contractor signed. |
| Voided | The date the change order was voided, if it was. A voided change order never counts. |
| Status | Calculated: Approved only when all three parties have signed and it isn't voided. |
| Contract Sum After | Calculated: the original contract sum plus every approved change order up to this row. |
On the Summary tab, enter the original contract sum and substantial completion date from the owner-contractor agreement.
Add a row for each change order when you issue it: number, date, description, reason, cost and time.
Enter each signature date as it comes back. The status turns Approved when all three are in.
If a change order is cancelled, enter the date under Voided instead of deleting the row, so the numbers stay in sequence.
Read the contract sum and substantial completion date to date on the Summary tab.
Agradium counts a change order only when the owner, architect and contractor have all signed, and voided orders never count. Each change order shows the original contract sum, the net change from earlier orders, and the new contract sum and time.
Questions
When the owner, architect and contractor have all signed it. Until then it is pending, so this log shows its value separately as awaiting signatures.
Enter the cost as a negative number. A credit lowers the contract sum to date the same way an addition raises it.
No. It is a log of your change orders, not the change order document itself. Issue each change order on the form your contract requires, and use the log to keep track of them.
Change management
RFIs, ASIs, proposal requests, CORs, CCDs and change orders compared: who starts each one, whether it changes cost or time, who signs, and how they connect.
5 min read
Excel workbook · 11 tabs
Every log in one workbook, with a summary of what is open, what is overdue and the contract sum to date.