ASI Log Template: Architect's Supplemental Instructions

An architect's supplemental instruction (ASI) clarifies the documents or makes a minor change with no change in cost or time. The log answers two questions on every project: which ASIs the contractor has accepted, and which ones turned into a priced change.

Download the Excel file

Free · .xlsx for Microsoft Excel · No sign-up

What's in the file

One log tab and a Summary tab. Each column heading in the file carries the same note as below.

ColumnWhat goes in it
ASI #Number ASIs in the order you issue them.
IssuedThe date you issued the ASI to the contractor.
DescriptionWhat the ASI clarifies or changes. An ASI carries no change in cost or time.
Drawings and SectionsThe sheets and specification sections it revises, for example A-201, 09 29 00.
RFI #The RFI that prompted it, if any.
Contractor AcceptedThe date the contractor accepted the ASI with no change in cost or time.
Contractor RejectedThe date the contractor said the ASI changes cost or time.
PR #The proposal request you issued after a rejection, to price the change.
StatusCalculated: Awaiting contractor, Accepted, Rejected (no proposal request yet), or the proposal request it moved to.

How to use it

  1. On the Summary tab, enter the project name and number.

  2. Add a row for each ASI when you issue it: number, date, description, the sheets and sections it revises, and the RFI that prompted it, if any.

  3. When the contractor accepts it with no change in cost or time, enter the date.

  4. If the contractor says it changes cost or time, enter the date under Contractor Rejected. The status shows Rejected until you issue a proposal request and enter its number.

When the spreadsheet gets busy

In Agradium, an ASI stays a draft until you issue it, so numbers never skip. When the contractor doesn't accept it, the proposal request that follows is linked to it, and the change is followed from the first question to the signed order.

Questions

Frequently asked questions

Can an ASI change the contract sum?

No. An ASI is issued on the basis that it changes neither cost nor time. If the contractor disagrees, the change moves to a proposal request and, once priced and agreed, to a change order.

What is the difference between an ASI and an RFI?

The contractor sends an RFI to ask a question. The architect issues an ASI to give an instruction, often because answering an RFI meant revising the drawings.

Should ASIs be numbered separately from RFIs?

Yes. Each document type has its own sequence, so ASIs run 1, 2, 3 regardless of RFI numbers. When an ASI answers an RFI, enter the RFI number in the RFI # column.

Keep going

Change management

What Is an ASI in Construction?

What an ASI (architect's supplemental instructions) is, when architects issue one, what it can't change, and what to do when the contractor disagrees.

6 min read

Excel workbook · 11 tabs

Construction Administration Log

Every log in one workbook, with a summary of what is open, what is overdue and the contract sum to date.

Free download

Excel

RFI Log

Due dates, consultant hand-offs, days open and overdue flags, calculated for you.

Free download

See your next project in Agradium.

A 30-minute walkthrough, from the first RFI to a signed change order.

Request a demo